Challenge
Holme Hall Quarry in South Yorkshire is owned and operated by the Breedon Group, a leading supplier of aggregates, cement, ready-mixed concrete, asphalt and specialist construction products. The quarry began operations in the 1930s and today produces over 2.4 million tonnes of limestone products each year. Throughout this time, Holme Hall Quarry has played a vital role in the local economy and community, the site employs many people from the surrounding areas, and its projects have contributed to several recent construction projects in the region.
Further excavation work in the quarry necessitated a new bridge construction to maintain existing public access over the new extraction site. The route typically needed to accommodate up to 45 cars and 35 HGV per day and was expected to be in service for at least five years. Not only did it need to be robust, withstanding the rigours of quarry life; it needed to be economical but also versatile enough to be installed on the pre-formed abutments of differing heights. A modular steel bridge solution was determined to be the ideal fit to meet each of these requirements.
Solution
Mabey Bridge designed and supplied a single span, 42m x 4.2m Compact 200™ to enable the extension of the road. Consulting engineers BT Bell prepared the sub-structure work (including abutments) and calculated the road alignment and levelling requirements to ensure that the bridge could be built to suit the existing road alignment, which was not level with one bank 1.1m lower than the other. This enabled the new bridge to be launched efficiently.
Result
Within ten days of commencing bridge construction, the access road became fully operational once again, enabling public traffic to drive safely over the ongoing extraction works.
Products

Bridge Design Services
Bridge design services to ensure your bridge meets your specification and is fit for purpose
view product
Bridge Installation Advice
Bridge installation advice to ensure a rapid, safe and trouble-free bridge-build.
view product
Mabey Compact 200
Mabey’s most popular modular bridging system. Supplied in a variety of spans and widths, and configured from pre-engineered components for ease of installation
view productRelated Projects

Chevron Oil Refinery Bridge, UK
Energy and Pipelines, Oil and Gas
Bridging, Engineering and Project Services
Pembroke, United Kingdom

Construction Site Access Solutions, Ireland
Construction
Bridging, Engineering and Project Services, Temporary Access and Roadways
Ireland

Swarkestone Quarry, UK
Construction, Infrastructure
Bridging, Engineering and Project Services
Barrow-on-Trent, UK