Challenge

Originally begun in 2006, the Farahantsana Bridge across the River Ikopa was to become an access route to the Mahitsy Hydro-electric Plant building project, but was abandoned by the previous investor. Part of the original work, the concrete abutments and piers for the river crossing, had already been installed, but the bridging itself hadn’t been started. In 2014 the Tozzi Green Group took over the project and began to scope out various bridging solutions to utilise the work that had already been done. The main challenge facing Tozzi was how to install a modular bridge, designed and erected to specific dimensions, onto an existing concrete structure – one which hadn’t been originally designed to fully match with a standard bridge.

Solution

During this process Tozzi contacted Mabey Bridge in order to find a viable, technical solution. Chosen because of their reputation in the region and expertise in modular bridging solutions, Mabey Bridge with its in-house design engineering team, proposed a bridge scheme that involved three modular sections, each with the ability to locate perfectly onto an abutment. Each section was to be designed to a ‘standard’ width, but required individual length spans – 27m, 34m and 26m; each section also needed to provide a load capacity that was more than sufficient for carrying construction traffic for the hydro-electric plant installation work.

Result

The construction of the new Farahantsana Bridge by local contractors meant that work could begin in earnest on building the hydro-electric plant.

The bridge not only provided access to the plant, but also benefited the rural communities of Ambohimasina and Ampanotokana, who can now take advantage of the development prospects and economic opportunities, owing to the improved connectivity. This is a vital project, which is set to supply 200,000 households with power by 2021 and strengthen Madagascar’s overall volume of production on the interconnected network of Antananarivo.

The President of the Republic in the presence of the President of the Senate, members of the government as well as representatives of Tozzi Green Group officially inaugurated the bridge in 2017, celebrating future prosperity for both the local communities and Madagascar as a nation.

Products

Bridge Design Services

Bridge design services to ensure your bridge meets your specification and is fit for purpose

view product

Mabey Compact 200

Mabey’s most popular modular bridging system. Supplied in a variety of spans and widths, and configured from pre-engineered components for ease of installation

view product

Mabey SmartEdge™ System

The Mabey SmartEdge™ System is a unique modular bridge accessory which can be personalised with bespoke graphics, logos and colours.

view product

browse more products

Related Projects

Lluto Bridge, Peru

SectorsConstruction, Energy and Pipelines

CategoriesBridging, Engineering and Project Services

LocationPeru

view project

Lom Pangar Hydro-Electric Dam, Cameroon

SectorsEnergy and Pipelines, Government, Infrastructure

CategoriesBridging, Temporary Access and Roadways

LocationLom Pangar, Cameroon

view project

view all projects